MOQ, Tier Pricing and the Real Cost of Splitting Colours

MOQ, Tier Pricing and the Real Cost of Splitting Colours

Summary

Splitting one linen order into more colours raises the unit price 5-15% at low volume because each colour adds a dye batch, a cutting set-up, trim minimums and an inspection lot. Here is where the money goes, how the tier index shifts, what it does to lead time, and five consolidation tactics that recover most of the gap.

MOQ, Tier Pricing and the Real Cost of Splitting Colours

Pricing & Order Planning

MOQ, Tier Pricing and the Real Cost of Splitting Colours

Ask three linen factories to quote the same 600-piece shirt programme and the totals will not match. Ask each of them to quote it in one colour, then in four, and the gap between those two answers tells you more about the supplier than either total does. Colour count is not a detail at the end of a purchase order. It sits directly on top of dye batch minimums, cutting set-ups and trim buying, and it moves both the unit price and the ship date.

In short: every additional colour creates a separate dye batch, a separate cutting lay and a separate set of trim and label minimums. At low order quantities that usually adds 5-15% to the unit price and 5-12 days to bulk lead time, even though the total piece count has not changed. This article breaks down where that money goes, shows how tier pricing is actually built, and sets out the consolidation tactics we use with brands to keep a four-colour range inside a single-colour budget.

It is written for brand owners, founders and sourcing managers placing linen orders in the 60-3,000 piece range, where the split penalty is largest and least visible. If you are still choosing between suppliers on headline price, the MOQ tiers guide for custom linen manufacturing explains the tier ladder itself; this piece is about what happens inside a tier when colours multiply.

60pcs MOQ per style per colour
25-35days bulk after approval
30-45%fabric share of unit cost
3-7%first-wash shrinkage

Why Colour Count Is a Cost Line, Not a Preference

A purchase order has four cost bases that scale with quantity and one that scales with variety. Fabric consumption, cutting time, sewing minutes and finishing all rise smoothly as piece count rises. Colour count is the exception: it multiplies fixed work while leaving the piece count unchanged. Four hundred pieces in one colour is one dye batch, one cutting lay per size, one trim purchase and one packing run. Four hundred pieces in four colours is four dye batches, four set-ups, four trim purchases and four packing runs for the same four hundred pieces.

That is why a factory cannot simply divide its one-colour price by four and hand you a colour assortment. The fixed portion of the price - the part that does not shrink when a run gets shorter - is being paid four times instead of once. In our own costing, the fixed and semi-fixed elements of a linen style typically sit between 15% and 25% of the unit price at 300 pieces in one colour. Spread the same 300 pieces across four colours and that fixed block is charged against 75 pieces per colour instead of 300, so its per-unit weight roughly quadruples.

The effect is easy to miss because quotations rarely show it. Most factories quote a single blended unit price, and the colour penalty arrives as a vague line such as "small colour surcharge" or simply as a higher price than the one discussed at sampling. Buyers then assume the factory moved. Usually the factory did not move; the order shape did.

The one-sentence version: splitting an order into more colours does not reduce the work in proportion to the pieces, so the fixed cost of dyeing, cutting, trimming and packing is divided by a much smaller number. That division, not the fabric price, is what you are paying for.

The Four Hidden Costs Inside a Colour Split

When a brand sends a four-colour order, four separate cost events fire. Each one is small on its own and each one is invisible in a blended quote.

Dye batch minimum

A dye vessel has a practical minimum load. Below it, the same water, steam, chemicals and machine time are spread over fewer metres, so the cost per metre climbs steeply. This is the largest single driver of a colour premium.

Cutting set-up per colour

Every colour is cut as its own lay to avoid shade mixing on the table. Marking, spreading, cutting and bundle ticketing repeat, and short lays waste more fabric at the ends of the marker.

Trim and label minimums

Thread, buttons, care labels, hangtags and polybags are bought in minimum packs. Four colours rarely need four times the trims, but suppliers still buy and hold four colour-matched sets.

QC and packing segregation

Inspection lots, shade band checks and carton segregation by colour all add handling. Under AQL 2.5 the same sample size is applied per colour lot, not per order.

The dye batch is where the money concentrates. A pale sand, a warm ecru and a soft sage may look like three separate products to a merchandiser, but to a dyehouse they are three recipes, three lab dips and three vessel loads. The comparison of yarn-dyed, piece-dyed and garment-dyed routes matters here, because a yarn-dyed check or stripe can deliver several visual colours from one fabric booking, which is a completely different cost structure from three piece-dyed solids.

How Tier Pricing Is Actually Built

Tier pricing is usually presented as a quantity ladder: more pieces, lower price. That is only half of it. A well-built ladder has two axes - total quantity and number of colours - because the factory's fixed cost depends on both. The table below is the model we use internally when a brand asks what a colour assortment will do to the price. It is an index, not a quotation, and it assumes the same style, the same fabric quality and the same construction throughout.

Colours in the styleMinimum total at 60 pcs/colourIndicative unit index (1 colour = 100)Typical added lead timeCost driver that starts to bite
160 pcs100baselinenone
2120 pcs103-106+2 to 4 dayssecond dye batch, second cutting lay
3180 pcs106-110+4 to 7 daystrim minimums, carton segregation
4240 pcs109-115+5 to 9 daysshort dye lots, extra lab dips
6360 pcs115-125+8 to 14 daysdye queue, per-colour inspection

Index values reflect our own quoting practice on mid-weight linen (140-190 GSM) in the 60-600 piece range. They are planning guidance, not a price list. Every quotation is built from the actual fabric, construction and colour references.

Two things in that table are worth pausing on. First, the index rises faster between one and two colours than between three and four. The second colour forces the second dye batch, which is the expensive step; the fifth and sixth colours add queue time more than they add unit cost. Second, the minimum total quantity is not a factory invention - it is simply MOQ multiplied by colour count. If our MOQ is 60 pieces per style per colour, then a four-colour style cannot be produced for less than 240 pieces. A brand that wants 60 pieces in four colours is not asking for a small order; it is asking for four small orders, and each one carries the full fixed burden of a small order.

This is also why tier ladders can look generous at 500 pieces and stingy at 150. The 500-piece tier has room to absorb a colour split; the 150-piece tier does not. When a brand compares quotes from two factories, the one with the lower 500-piece price may simply be assuming fewer colours, or assuming that colour splitting will be charged later as an extra.

What a Split Does to Lead Time

Lead time damage is usually larger than the price damage, and it is the part brands plan worst. Our standard bulk window is 25-35 days from approved pre-production sample and confirmed lab dips. That window assumes a dye programme that can run in parallel with cutting preparation. A colour split breaks that parallelism in three places.

  1. Dye queue. Each colour is a separate vessel load, and dyehouses schedule by depth of shade and machine availability. Four colours do not necessarily run on four machines; they may queue behind each other. Adding two to five days per additional batch is normal in peak season.
  2. Lab dip approval. Every colour needs its own lab dip approved before bulk dyeing, and each dip consumes a round of courier time. If a brand reviews dips weekly, three colours can burn two extra weeks before the first metre is dyed.
  3. Sequential cutting and sewing. Lines are set by colour to avoid shade mixing at the machine. A line that finishes one colour on day nine cannot start the next colour on day one, so the tail of the schedule extends.

The practical consequence: a four-colour order placed on the same day as a one-colour order will not ship on the same day, even at identical total quantity. In our experience the gap is 5-9 days for four colours and 8-14 days for six, which is consistent with the table above. For a brand planning a drop date, that gap is the difference between full-price sell-through and a markdown.

Plan backwards from the drop, not forwards from the PO. Take the retail or wholesale ship date, subtract 7-10 days for sea freight booking and 3-5 days for final inspection, then subtract the split-adjusted bulk window. If the resulting approval date is in the past, the colour count - not the factory - is the thing to renegotiate.

The interaction with cost is not linear either. A split that pushes production into a peak dye month can add both days and money, because the factory has to buy queue priority or book fabric earlier than planned. Our article on the seven cost drivers behind custom linen clothing covers the other six; colour count is the one that most often gets missed in the first quote.

The Split Penalty in Low-MOQ Linen Orders

The penalty is mild at 2,000 pieces and brutal at 120. At 2,000 pieces, four colours means 500 pieces per colour, comfortably above any dye minimum, and the fixed cost is diluted to a rounding error. At 120 pieces, four colours means 30 pieces per colour - below our 60-piece per-colour MOQ - so the order is either refused, consolidated, or priced as four minimum runs.

This is the single most common misunderstanding we handle in first enquiries: a brand reads "MOQ 60 pcs" and plans a 60-piece launch across four colourways. The MOQ applies per style per colour, so that plan is a 240-piece order. When the brand insists on 60 total, the realistic options are one colour, or a two-colour split at 30 each with a surcharge, or moving to a stock fabric where a shorter dye run is not required.

Stock fabric changes the arithmetic completely. We hold more than 50 fabric specifications in stock, and a stock colour can be cut without any dye batch at all. The colour premium then collapses to cutting and trim costs, typically 2-5% instead of 9-15%. The trade-off is palette: stock shades are a fixed list, and a brand that needs an exact Pantone reference is back in the dye programme. The small-batch production playbook sets out how to sequence a first collection around that constraint without looking like a compromise.

Do the division before the design review. Total pieces divided by colours must clear 60. A six-colour capsule at 300 pieces fails that test at 50 per colour, and no amount of negotiation fixes it - the order shape has to change.

Five Ways to Reduce the Split Penalty

Consolidation is not about talking a brand out of its palette. It is about getting the same visual range through fewer cost events. These are the five levers that move the number most, in descending order of effect.

1. Consolidate into one shade family and one dye recipe

Three tones built from the same base recipe - a sand, a stone and a taupe, for example - can sometimes be dyed as one batch with shade adjustment, or at least sequenced back to back on the same machine. The palette still reads as a range to the customer, but the dyehouse sees one family. This is the highest-leverage move available and it costs nothing except a colour meeting.

2. Use stock fabric for the volume colour and dye only the accent

Put 70-80% of the order into a stock shade and dye one accent colour for the story. The stock portion carries no dye premium; the accent carries one batch instead of four. Unit cost typically lands within 3-6% of a single-colour order while still shipping a two-tone range.

3. Raise depth per colour instead of breadth

Retail data usually rewards depth on the bestseller more than breadth across six shades. A 240-piece order in two colours of 120 each will out-perform a 240-piece order in four colours of 60 each on both cost and sell-through, because the four-colour version pays four fixed loads and still leaves each colour too thin to reorder. The linen fabric cost guide shows how fabric booking volume interacts with this decision.

4. Split the delivery, not the dye batch

If the constraint is cash or warehouse space rather than colour, keep one dye batch and ship in two waves. You keep the single-batch price and the single cutting set-up, and you spread the payment. This is often what a brand actually needed when it asked for a colour split.

5. Move colour into the fabric construction, not the dye

A yarn-dyed stripe, check or melange gives multiple visual colours from one fabric booking and one dye programme. The fabric costs more per metre than a solid, but it can replace two or three solid colours entirely. For brands with a print or texture story, this is often the cheapest route to a multi-colour range.

In practice we combine levers two and three most often: one stock volume colour, one dyed accent, depth loaded onto the volume shade. That structure routinely brings a four-colour brief within 5% of its one-colour equivalent while keeping the assortment story intact.

How to Ask for a Colour-Split Quote

Most colour premiums are quoted blind because the enquiry did not contain the information needed to price the split. A factory that receives "300 pcs, four colours, linen shirts" has to assume the worst case: four deep shades, four lab dips, four short dye lots, one ship date. Give the following and the quote usually comes back lower, because the assumptions disappear.

  • Style count and colour count separately. "Two styles, four colours total" and "two styles, four colours each" are different orders with different fixed costs.
  • Pieces per colour, not just total. The per-colour depth is the number that decides whether a dye batch is viable.
  • Colour references. Pantone TCX numbers, physical swatches, or "match stock shade X". A reference is cheaper than a description.
  • Fabric specification. Weight in GSM, weave, and whether stock or dyed-to-order. Our range runs 100-260 GSM; weight changes dye vessel loading.
  • Target ship date and drop date. If they differ, say so - it opens the split-delivery option.
  • Size curve. A curve skewed to one size cuts more efficiently and can absorb a colour without a full extra lay.
  • Labelling and packaging per colour. Separate SKUs, hangtags and cartons per colour add handling that must be priced.

Our standard response time is a 48-hour initial report and a full quotation within 3-7 working days, and that only holds when the enquiry carries the seven items above. A complete brief also makes the tier conversation honest: the factory can show which colour is expensive and which is nearly free, instead of hiding the average in one number.

Terms That Protect Both Sides

Colour splits create commercial arguments later unless the order document settles four points up front. These are not legal formalities; each one maps to a cost the factory has already taken on.

TermWhat to writeWhy it matters on a split order
Minimum per colourState pcs per colour and accept that the total cannot fall below MOQ × coloursPrevents a late reduction that turns a viable batch into a short run
Dye lot toleranceAgree the shade tolerance and the inspection light sourceColours dyed in separate batches will never be identical; the tolerance decides what passes
Lab dip approval windowFix the number of dip rounds included and the days allowed to approveEvery extra round adds days to a schedule already extended by the split
Over/under deliverySet a percentage band per colour, not per orderShort dye lots deliver unevenly; a per-order band hides a short colour

The lab dip clause deserves emphasis. On a one-colour order, a slow approval costs a day. On a four-colour order, it costs four days minimum, because dips are usually approved in sequence and bulk dyeing waits on the last one. Brands that batch their comments into a single consolidated reply routinely save a week. The same discipline applies to the commercial side; the negotiation guide on pricing, MOQ and payment terms covers how to trade colour flexibility against price without reopening the whole quote.

When Splitting Still Makes Sense

None of this argues for permanent single-colour orders. A split is the right decision in four situations, and in each the premium buys something real.

  • You are testing colour demand. Two or three colours at low depth is cheaper than a stock-out on the wrong shade, provided the total clears the per-colour minimum.
  • You sell through multi-brand stockists. Each stockist may need a different colourway, and the assortment is the product.
  • The colour is the design. Garment-dyed pieces where shade variation is the aesthetic justify separate batches by definition.
  • You are reordering a proven bestseller. Once a shade has sold, consolidating the reorder into one deep batch is the cheapest production you will ever run.

The decision rule we give brands is simple. Split when the colour carries commercial information you do not yet have; consolidate when it does not. A first drop with unknown demand earns its premium. A repeat order for a shade that already sold through does not - it is paying a fixed cost for variety nobody asked for.

Frequently Asked Questions

Does splitting an order into more colours always increase the price?

Almost always, unless the total quantity is high enough to keep every colour above the dye batch minimum. At 2,000 pieces in four colours the premium can be under 3%; at 240 pieces in four colours it is typically 9-15%.

Is MOQ charged per colour or per order?

Per style per colour, at 60 pieces. A four-colour style therefore starts at 240 pieces. This is the rule that surprises first-time buyers most.

Can I get four colours at 60 pieces total?

Not as four dyed colours. The realistic options are one colour at 60 pieces, a two-colour split with a surcharge, or stock fabric shades that need no dye batch.

How much extra lead time should I plan for?

Roughly 2-4 days for a second colour, 5-9 days for four, and 8-14 days for six, on top of the 25-35 day bulk window. Lab dip approvals can add more if comments arrive slowly.

Why does one extra colour cost so much at low volume?

Because the fixed work - dye vessel load, cutting set-up, trim minimums, inspection lot - repeats in full while the piece count per colour falls. You are dividing the same fixed cost by a much smaller number.

Can stock fabric avoid the colour premium?

Mostly, yes. A stock shade skips the dye batch entirely, so the premium drops to cutting and trim costs, usually 2-5%. The limitation is that stock shades are a fixed list rather than any Pantone reference.

Does garment dyeing make splits cheaper?

Not cheaper, but more flexible. Garment dyeing allows smaller batches per colour and late colour decisions, at a higher per-unit cost and with deliberate shade variation.

Next Step

The fastest way to find out what a colour split costs on your own range is to send the order shape before the design is finalised: styles, colours, pieces per colour, fabric weight and target ship date. We will come back within 48 hours with an initial read on which colours are expensive and which are nearly free, and a full quotation within 3-7 working days.

If you are still building the range, the capsule collection costing model shows how style count and colour count interact before a single sample is cut. When you are ready to price an actual order, send us the brief through our contact page and we will quote the split honestly, line by line.