How Do I Plan Linen Fabric Reorders?

How Do I Plan Linen Fabric Reorders?

Fabric Planning · Linenwind

How Do I Plan Linen Fabric Reorders?

Plan a linen fabric reorder by working backwards from the date the goods must be on shelf, not forwards from the day you notice a size is selling out. In practice that means four things: keep a written fabric card with a retained approval swatch, calculate a reorder point from real consumption rather than the tech pack, decide which colors stay on stock fabric and which justify custom dyeing, and book the mill slot before the sell-through signal is unambiguous. For a typical program the fabric decision must be made about ten to fourteen weeks before the retail date, because bulk production alone runs 25-35 days after approval and sampling adds 7-12 days.

60 pcs MOQ per style and color 25-35 days bulk 3-7% first-wash shrinkage 50+ stock fabric specs

What a Linen Reorder Plan Actually Contains

A reorder plan is not a purchase order with a new date on it. It is a small set of documents and decisions that together allow a second production run to deliver the same garment the customer already bought. Three components carry most of the weight, and each one fails in a different way when it is missing.

Fabric standard

The mill article, composition, yarn count, construction, finished GSM, width, finish route, shade reference and shrinkage figure, with a retained swatch of the approved lot. Without it, "same fabric" becomes an instruction each supplier interprets differently.

Quantity and timing

Actual consumption per garment, weeks of cover, the confirmed mill lead time for that exact quality, and the minimum run per color. These four numbers decide whether the reorder is economic and when the booking has to be released; the tiering logic behind the 60-piece threshold is set out in this guide to MOQ tiers.

Approval and QC

The signed sample, the AQL 2.5 acceptance level, the inspection timing and the rule for a lot that fails marginally. Agreeing the rule before the lot arrives is what keeps quality a system rather than a negotiation.

Brands that already run a documented first order usually have most of this material scattered across emails, tech packs and photographs. The planning work is largely consolidation: put it in one versioned document per quality, name an owner, and require the purchase order to reference it. The garment-side calendar is covered in this guide to linen clothing lead times, which explains where each stage sits relative to the others.

The Seven-Step Reorder Plan

Run these steps in order. Each one produces an input the next step needs, and skipping a step usually means rebuilding the plan later under time pressure.

1

Confirm the fabric still exists as specified

Ask the mill whether the article is still in production, whether the base cloth is stocked, and whether the finishing route is unchanged. A quality that has been quietly re-sourced is a new quality, even if the article number looks familiar.

2

Rebuild consumption from the cutting room

Use the marker consumption and the waste actually recorded on the last bulk order. Linen markers lose more than buyers expect because the weave shifts and defects must be cut around, so theoretical consumption systematically understates the requirement.

3

Choose the color route

Decide which colors repeat on stock fabric and which justify custom dyeing. Custom dye buys an exact shade and costs a minimum run plus a dyeing slot; stock fabric buys speed and a known price but limits the palette. The two-tier structure of signature colors plus stocked core colors is the most common compromise.

4

Calculate the reorder point

Multiply max weekly usage by max lead time, subtract average weekly usage multiplied by average lead time, and treat the result as safety stock. Add the usage expected during the normal lead time to get the trigger point. Express the answer in metres, not garments.

5

Book the slot before the trigger is reached

A reorder point is a decision date, not a purchase date. The booking has to be released early enough that the mill slot, the dyeing queue and the finishing capacity are all secured before the stock position becomes urgent.

6

Re-test the incoming lot

Check shrinkage after the labelled wash, colourfastness to washing, light and rubbing, and handfeel against the retained swatch. A report should state the method used, because a result without a method cannot be compared with the previous lot.

7

Cut by lot and record the outcome

Keep separate dye lots in separate SKU or warehouse positions, sell the older lot first, and update the fabric card with anything that changed. The card is only useful if it reflects what actually arrived, not what was originally ordered.

The Numbers Behind the Plan

NumberHow to get itTypical range for linen programs
Fabric per garmentMarker consumption plus actual cutting wasteDepends on style; verify from last bulk
Weeks of coverUnits on hand divided by average weekly sales over eight weeks8-12 weeks for stable repeat styles
Sampling timeWritten schedule from the factory7-12 days, with a 7-14 day window
Bulk productionConfirmed after sample approval25-35 days
First order cycleApproval through delivery35-60 days
Minimum orderPer style and per color60 pcs
First-wash shrinkageTest against the printed care instructions3-7%
Fabric weight rangeFinished GSM, measured after finishing100-260 GSM across the range
Inspection levelAgreed in the purchase orderAQL 2.5

Figures describe standard practice for custom linen apparel produced in China. Confirm the specific construction, finish and season with the mill before committing a booking.

The worked example that follows uses illustrative numbers only, because the correct buffer depends on each brand's own variance. Assume a style selling 40 units per week with a peak week of 60, a quoted bulk lead time of 25-35 days, and 45 days allowed for booking and inspection delays. Safety stock is 60 multiplied by 6.4 weeks, minus 40 multiplied by 5.1 weeks, which is roughly 384 minus 204, or about 180 units of fabric equivalent. The reorder point then sits near 384 units, because it includes the 204 units consumed during a normal lead time.

Two refinements make the calculation usable. First, review the buffer whenever the sales pattern changes, since a style that moves from one channel to three has a different variance. Second, hold the buffer in the fabric that can actually be cut, not in a color that has stopped selling. A buffer in the wrong color is a write-down with extra steps.

Batch Consistency Checklist for Every Reorder

Shade and handfeel variation between lots is normal in natural fibre. The planning objective is containment: define the standard, verify each lot, and prevent two lots from meeting inside one garment or one shelf fixture.

Run this checklist when the fabric arrives, before any cutting starts. It takes less time than one email thread about a shade complaint.

Physical approval swatch available and dated
Mill batch and article number recorded
Shade compared in agreed lighting, not on screen
Shrinkage re-tested after the labelled wash
Colourfastness checked for washing, light and rubbing
Handfeel and drape compared with the retained swatch
Usable width confirmed against the marker
Lot separated at SKU level before cutting

The tests themselves are routine: dimensional stability after the specified home wash, colourfastness to washing with assessment of shade change and staining, colourfastness to light and to rubbing, and a visual comparison for surface defects, slubs and hairiness. Methods such as the ISO 105 series or the equivalent AATCC procedures are the usual reference, and the acceptance limit should be written into the purchase order rather than agreed after the result is known. The wider logic of what to test and why is set out in this guide to linen fabric testing.

Stock Fabric or Custom Dye for the Repeat?

This is the decision that most directly determines reorder speed. It is usually framed as a color question, but it behaves like a cash and calendar question.

Stock fabric wins on speed

No dyeing slot is needed, so sampling can run in 7-12 days and a repeat can be booked against cloth the mill already holds. Ideal for core colors, test styles and tight launch dates.

Custom dye wins on shade

You get the exact color to your standard and a defensible seasonal story, at the cost of a minimum run per color and a position in the dyeing queue.

Two-tier palettes reduce risk

Two or three signature colors on custom dye, the rest on stocked qualities. This keeps the brand visually coherent while preserving the ability to replenish quickly.

Ask about discontinuation

A stocked article that disappears without notice is worse than a custom quality with a known minimum. Ask what notice the mill gives before discontinuing a quality you depend on.

Cost should be compared per route rather than per kilogram. Fabric represents roughly 30-45% of garment cost, and the difference between stock and custom shows up less in the headline price than in minimum runs, waste and the markdown risk of an over-ordered color. With a minimum of 60 pieces per style and color, the practical limit is usually how many colors a reorder can support, not how many the design team would like. The fabric cost structure is broken down in this fabric cost breakdown.

Building the Backward Calendar

Start from the date the goods must be available to sell, then subtract each stage in reverse. The result is the date the fabric decision has to be made, which is the only date in the plan that cannot move.

  1. Fix the on-shelf date from the retail or wholesale delivery window, not from an internal launch meeting.
  2. Subtract warehouse receiving, counting and inspection, including any minor rework.
  3. Subtract freight and customs using the forwarder's current estimate for the route and season.
  4. Subtract bulk production at 25-35 days, then sampling at 7-12 days plus the approval loop.
  5. Subtract the mill's fabric lead time for that exact quality, including the dyeing queue for custom shades.
  6. Add one to two weeks of decision buffer, so a late approval does not move the season.
StageWhat it coversPlanning allowance
On-shelf dateRetail or wholesale delivery windowFixed by the channel
DC receiving and QCUnloading, counting, inspection, minor reworkConfirm with your warehouse
Freight and customsTransit plus clearance for the route and seasonUse the forwarder's current estimate
Bulk productionSewing, finishing, packing25-35 days after approval
Sampling and approvalSample making, comments, second round7-12 days, plus approval time
Fabric bookingLoom slot, dyeing queue, finishingConfirm in writing per quality
Decision bufferAbsorbs a late approval or a missed reply1-2 weeks

For a first order the full cycle is typically 35-60 days from approval to delivery. A reorder removes development rounds but not the fabric or production stages.

Once the calendar exists, the seasonal rhythm becomes easier to manage. Book capacity in the quiet window for the busy one: if a repeat is needed for the second quarter, the fabric booking belongs in the first, before the summer program absorbs the looms. The period around Chinese New Year deserves particular attention, because the shutdown compresses both the weeks before and the weeks after. The capacity picture is explained in this guide to booking linen capacity before Chinese New Year 2027.

Repeat orders also behave differently from first orders in the commercial steps. The specification and sample already exist, so the negotiation is about quantity, price and slot rather than development. The mechanics are described in this guide to repeat orders with a linen manufacturer.

A short lead time quoted during peak season is not a plan. Ask which line, which dyeing slot and which finishing window the promise refers to, and get the answer in writing on the purchase order. A date that depends on an unbooked slot is an intention, and intentions do not ship.

What Good Reorder Planning Looks Like in Practice

A well-run repeat has a calm quality to it. The fabric card exists before the first order ships, the retained swatch is filed with the batch number, the reorder point is in the merchandising report rather than in someone's memory, and the booking date appears on the product calendar months before the season starts. When the sell-through signal arrives, the decision is already half made. The quality question that usually follows is answered in this answer on reorder consistency.

The measurable signs are equally simple. Watch four indicators and the planning conversation stays factual:

  • Weeks of cover stays inside its planned band instead of drifting up before a season and collapsing after it.
  • Shrinkage results on incoming lots sit inside the approved figure, tested with the care instructions you actually print.
  • On-time delivery holds across two consecutive repeats, which is the only real evidence that the quoted lead time is a commitment.
  • Reorder sell-through justifies the quantity booked, rather than clearing at markdown two months later.

When one of those indicators drifts, the fabric card and the backward calendar show exactly which assumption moved, which is the difference between fixing a plan and guessing at a cause.

For a brand running several qualities, the same discipline scales by standardising where the customer cannot see a difference: shared finish routes, shared base cloths, and a palette built around a small number of signature colors. That standardisation is what makes a broad range replenishable at a minimum of 60 pieces per style and color, instead of forcing every color into its own dye run.

[IMAGE_PLACEHOLDER: 明亮仓库中亚麻面料卷材分层码放,每卷挂有批次标签,一位 merchandiser 手持留样色卡与新款剪样在自然光下比对,暖中性色调,纪实摄影风格]

Planning a repeat program for linen?

Send the style, the target quantity and the delivery window. We will confirm the fabric quality, the current sampling and bulk lead times, and the color route that fits your calendar. New inquiries receive an initial reply within 48 hours and a quotation in 3-7 working days.

Contact Linenwind Review linen lead times

Source: Linenwind, a B2B linen clothing manufacturer in Dongguan with OEM and ODM capability. Standard terms referenced: 60 pcs minimum per style and color, sampling 7-12 days, bulk 25-35 days, first order 35-60 days, sample fee USD 40-150 refundable, 50+ stock fabric specifications, AQL 2.5 inspection, ISO 9001, OEKO-TEX Standard 100 and SEDEX certification, fabric 30-45% and labour 25-35% of cost, first-wash shrinkage 3-7%, fabric weight 100-260 GSM.